Ground systems could delay Artemis 2 launch
Top Stories Tamfitronics The mobile launch platform that will be used for Artemis 2 was rolled back to the Vehicle Assembly Building Oct. 3 after tests at Launch Complex 39B. Credit: NASA/Jamie PeerMILAN — Refurbishment of ground systems like a mobile launch platform could become another factor in the schedule for the Artemis 2 mission that NASA says is still planned for launch next September.A report by the Government Accountability Office Oct. 17 found that work on the Exploration Ground Systems (EGS) program, which includes the mobile launcher and other ground systems needed to support launches of the Space Launch System and Orion spacecraft, could delay the Artemis 2 launch.“While EGS elements are close to completion, the program has no schedule margin for these remaining activities,” the GAO report stated. While issues with Orion led...